BAB A44, Düsseldorf - Velbert | New construction of the Angerbach viaduct | Final shoring 1st construction phase

On April 6th and 7th, the fifth and final shunting of the northern construction section of the Angerbach viaduct was successfully carried out. The 101.58 m shifting distance was carried out with the help of strand jacks.

In the coming months, the assembly of the end cross girders, the stacking of the bridge and the retooling of the cycle cellar for the southern superstructure will take place.

IGS Ingenieure GmbH & Co. KG is represented in this project with the areas of construction management and quality assurance steel construction and covers the tasks of site management, local construction supervision and welding and corrosion protection production supervision in the plant and on the construction site.